Doomadgee water supply project
Delivered in partnership by the Australian Government and Queensland Government.
Work has begun on the project to design and construct water infrastructure upgrades including:
- new pre-treatment, improved chemical storage and dosing systems, new clarifiers and filters, UV treatment, associated pipework and pumps, instrumentation and control system known as SCADA to monitor and control the treatment processes.
- new 2ML treated water reservoir integrated with existing reservoirs storage and connections to provide additional treated water storage.
The project team will consult with all stakeholders throughout the project. They will work closely with Doomadgee Aboriginal Shire Council and the local community to consider water safety and reliability issues.
| Phase of project | Start date |
|---|---|
| Stakeholder consultation | June 2025 |
| New treated water reservoir - finalise design and start construction (completed) | Late 2025 |
| New treated water reservoir - infrastructure commissioned and operational | September 2026 |
| Water treatment plant upgrades - process review (completed) | Early 2025 |
| Water treatment plant upgrades - detailed design (completed) | March 2026 |
| Water treatment plant upgrades - construction activities commenced | May 2026 |
| Water treatment plant upgrades - infrastructure commissioned and operational | Early 2027 |
More information
- Understand more about the Australian Government’s investment in water infrastructure projects for First Nations communities through its National Water Grid Fund (NWGF)
- Read about other Queensland projects funded through the NWGF
- How to use water wisely
- Contact engineering@dlgwv.qld.gov.au.