Doomadgee water supply project

Delivered in partnership by the Australian Government and Queensland Government.

Work has begun on the project to design and construct water infrastructure upgrades including:

  • new pre-treatment, improved chemical storage and dosing systems, new clarifiers and filters, UV treatment, associated pipework and pumps, instrumentation and control system known as SCADA to monitor and control the treatment processes.
  • new 2ML treated water reservoir integrated with existing reservoirs storage and connections to provide additional treated water storage.

The project team will consult with all stakeholders throughout the project. They will work closely with Doomadgee Aboriginal Shire Council and the local community to consider water safety and reliability issues.

Phase of projectStart date
Stakeholder consultationJune 2025
New treated water reservoir - finalise design and start construction (completed)Late 2025
New treated water reservoir - infrastructure commissioned and operationalSeptember 2026
Water treatment plant upgrades - process review (completed)Early 2025
Water treatment plant upgrades - detailed design (completed)March 2026
Water treatment plant upgrades - construction activities commencedMay 2026
Water treatment plant upgrades -  infrastructure commissioned and operationalEarly 2027