Aurukun water supply improvement project
The Queensland Government and Aurukun Shire Council are delivering this project as part of our commitment to the Closing the Gap national agreement. The Aurukun water supply improvement project will ensure reliable access to clean drinking water for community growth.
Work has begun to upgrade the water supply infrastructure for Aurukun. Upgrades include:
- review of raw water infrastructure
- improved chemical storage, new filtration, UV treatment and dosing systems and associated pipework and pumps
- instrumentation and a Supervisory Control and Data Acquisition (SCADA) system to monitor and control the treatment processes
- replacement of steel storage tank.
The project team will consult with all stakeholders throughout the project. They will work closely with the Aurukun Shire Council and the local community to consider water safety and reliability issues.
| Phase of project | Start date |
|---|---|
| Water treatment plant upgrades—concept design (completed) | April 2026 |
| Stakeholder consultation (completed) | June 2026 |
| Water treatment plant upgrades – detailed design (completed) | July 2026 |
| Construction activities commence | September 2026 |
| Infrastructure commissioned and operational | Mid 2027 |
More information
- Read more about the Closing the gap priorities fund.
- Read more about how we work closely with Aboriginal and Torres Strait Islander communities through a range of policies, projects and programs.
- How to use water wisely.
- Contact: engineering@dlgwv.qld.gov.au.