Current stage

Description

  • Extension of the existing Ensham Mine
  • Single seam, underground bord and pillar mining operations to extract thermal coal at the current planned production rate of 4.5 million tonnes per annum within existing mining leases and extension into a new mining lease area
  • Use of existing underground and surface infrastructure including road, rail and mine infrastructure equipment
  • No additional surface infrastructure or surface disturbance within the new mining lease area

Proponents

Ensham Join Venture including:

  • Idemitsu Australia Resources Pty Ltd
  • Bligh Coal Limited
  • Bowen Investment (Australia) Pty Ltd

Location

  • Approximately 35 kilometres (km) east of Emerald and 49km north-west of Blackwater in Central Queensland

Local government

  • Central Highlands Regional Council

Lifespan

  • Extension of existing mine to approximately 2037

Jobs

  • Maintaining current operational workforce of approximately 603
  • No construction workforce

Commonwealth approval needed

  • Yes (controlled action EPBC 2020/8669), single EIS assessment process for Queensland and the Commonwealth.

Environmental impact statement (EIS)

The process for the assessment of this project is as follows:

  1. Submission of draft TOR
  2. Public notification of draft TOR
  3. Final TOR issued (EIS in preparation)
  4. Public notification of EIS
  5. Proponent responds to submissions
  6. Project assessment report

The proponent is currently preparing the EIS.

Notice and documents

Publicly available documents can be obtained by accessing the links below or by contacting Idemitsu on 07 3222 5600, or emailing enquiries@idemitsu.com.au

When the EIS is released, public submissions will be invited. For further information about the EIS process for this proposal, contact the EIS Coordinator (Ensham Life of Mine Extension Project) on 13QGOV (13 74 68) or email eis@des.qld.gov.au